Rock Check Dam Spacing

Spacing between rock check dams in a channel or swale, where the toe of each upper dam sits at the crest of the next.

Run the calculator

Example

You enter

You get

Checked against published worked examples from: Iowa SUDAS.

Details, formula, and sources

Scopespacing = dam height / channel slope, dams = ceil(reach / spacing). A 2 ft dam in a 4% channel spaces at 50 ft (6 dams over 300 ft); on an 8% grade the spacing halves and the count doubles. Small channels only; the AHJ governs.

Formula or tablespacing_ft = dam_height_ft / (channel_slope_pct / 100); dams = ceil(reach_length_ft / spacing_ft).

Source and editionCrest-to-toe check-dam spacing identity by name (the toe of each upper dam at the crest of the next); first-principles geometry.

Free accessThe crest-to-toe spacing rule is public erosion-control practice.

What governsEstimate. AHJ and licensed professional govern.

API field namesdam_height_ft, channel_slope_pct, reach_length_ft, spacing_ft, dams