Roller Compaction Production Rate

Surface coverage (sf/hr, sy/hr) and compacted cubic yards per hour a roller turns out from the drum width, speed.

Run the calculator

Example

You enter

You get

Checked against published worked examples from: US Army.

Details, formula, and sources

ScopeLift thickness, and passes - the production that sizes the fill schedule and the number of rollers. The test strip sets the passes.

Formula or tablearea_sf_hr = drum_width x speed x 5280 x efficiency / passes; area_sy_hr = area_sf_hr / 9; production_ccy_hr = area_sf_hr x (lift/12) / 27 = 16.3 x width x speed x lift x efficiency / passes (16.3 = 5280 / (12 x 27)).

Source and editionRoller production identity by name (compacted volume rate from coverage and lift); first-principles unit-folding arithmetic.

Free accessThe roller coverage-rate identity is published earthmoving practice; the 5280 / 12 / 27 unit constant is exact.

What governsEstimate. AHJ and licensed professional govern.

API field namesdrum_width_ft, speed_mph, lift_in, passes, efficiency, area_sf_hr, area_sy_hr, production_ccy_hr