Cutter Suction Dredge Production and Slurry Density

Turns pipeline flow and solids concentration into in-situ production and the specific gravity the discharge density...

Run the calculator

Example

You enter

You get

Details, formula, and sources

Turns pipeline flow and solids concentration into in-situ production and the specific gravity the discharge density gauge should read. The worked 24 in line at 15% solids makes 1,885 cy/h, of which 754 cy/h is the void space the sand had in the bank and is paid for. Contract porosity and effective-hour accounting govern.

flow = pipe area x velocity; solids = flow x Cv; in-situ = solids / (1 - porosity); production in cy/h = in-situ cu ft/s x 3,600 / 27; slurry SG = 1 + Cv (SG_solids - 1).

Continuity and volumetric bookkeeping. The pay quantity, the in-situ porosity assumed, and effective-hour accounting come from the dredging contract and the site's own material.

Public relations; no purchased standard is required to reproduce them.

Estimate. AHJ and licensed professional govern.

Field names used by the API: pipe_diameter_in, velocity_fps, concentration_pct, porosity, solids_specific_gravity, effective_hours, alternative_concentration_pct, area_ft2, flow_cfs, solids_cfs, in_situ_cfs, production_cy_per_hr, production_cy_per_day, solids_cy_per_hr, slurry_specific_gravity, alternative_production_cy_per_hr, alternative_gain_pct