Landfill Gas Generation (First-Order Decay)

Sums first-order decay across placement years to the peak at closure.

Run the calculator

Example

You enter

You get

Details, formula, and sources

Sums first-order decay across placement years to the peak at closure, then converts methane flow to heat rate and generating capacity and decays it forward. The worked site peaks at 3.1 MW collected and falls to 45% of that twenty years on. Generation is not collection, and the difference is the site's own emission.

Q = sum over placement years of k x L0 x M x e^(-k t); capacity = methane flow x heating value x generator efficiency, decayed forward as e^(-k t).

First-order decay, with the Clean Air Act default methane yield of 100 cubic metres per megagram and a methane generation rate constant of roughly 0.02 arid, 0.04 conventional, and 0.05 to 0.07 wet or bioreactor.

The model and its defaults are published by the EPA and are freely available.

Estimate. AHJ and licensed professional govern.

Field names used by the API: annual_tons, placement_years, methane_yield_m3_per_mg, decay_constant_per_year, methane_fraction_pct, collection_efficiency_pct, methane_heating_value_btu_per_cf, generator_efficiency_pct, annual_megagrams, decay_sum, methane_m3_per_year, methane_cfm, landfill_gas_cfm, heat_rate_mmbtu_per_hr, gross_capacity_kw, collected_capacity_kw, capacity_10yr_kw, capacity_20yr_kw