Transfer Station Throughput and Trailer Loadout

Sizes unloading positions from the peak hour rather than the daily average, the trailer fleet from the round trip.

Run the calculator

Example

You enter

You get

Details, formula, and sources

Sizes unloading positions from the peak hour rather than the daily average, the trailer fleet from the round trip, and the tipping floor from how long the trailers can be late. The worked station needs 2 positions against 1 on the average, 12 trailers, and 8,100 sq ft to absorb a 2 hour delay.

peak hour tonnage = daily tonnage x the peak share; unloading positions = peak arrivals x floor time; trailer loads = tonnage / payload rounded up; fleet = loads / (operating hours / round trip); surge floor = delayed tonnage / loose density / pile depth x a manoeuvring factor.

Queueing and volumetric arithmetic. The facility's own scale records, its permit's throughput limit, and the traffic study govern.

Public arithmetic; the arrival profile is the facility's own data.

Estimate. AHJ and licensed professional govern.

Field names used by the API: daily_tons, operating_hours, peak_hour_share_pct, collection_payload_tons, floor_time_min, trailer_payload_tons, trailer_round_trip_hr, loose_density_lb_per_cy, pile_depth_ft, manoeuvring_factor, loadout_delay_hr, peak_hour_tons, peak_arrivals_per_hour, unloading_positions, average_positions, trailer_loads_per_day, loads_per_trailer, trailer_fleet, surge_tons, surge_cy, surge_floor_sqft