Landfill Working Face Cell and Lift Volume

Daily cell volume, face advance, exposed surface, and cover for a working face.

Run the calculator

Example

You enter

You get

No published worked example is on file for this calculation. It is checked against a hand-worked derivation of its method and an independent reference test.

Details, formula, and sources

ScopeWith the same figures at a narrower face. Halving the width doubles the advance, so the top area does not move and the whole 23% cover saving comes off the sloped face. Density lost to a crowded face costs more than the cover saves.

Formula or tabledaily cell volume = tonnage / in-place density; face advance = volume / (width x lift height); sloped face length = lift height x sqrt(1 + run^2); cover volume = exposed top and face area x cover depth.

Source and editionGeometry. The approved operations plan and the permit govern the working face size, the lift, and the cover.

Free accessPublic arithmetic; the face size and lift are in the site's operations plan.

What governsEstimate. AHJ and licensed professional govern.

API field namesdaily_tons, in_place_density_lb_per_cy, face_width_ft, lift_height_ft, face_slope_run, cover_depth_in, layer_thickness_ft, passes_per_layer, narrow_face_width_ft, daily_volume_cy, advance_ft_per_day, slope_length_ft, top_sqft, face_sqft, exposed_sqft, cover_cy, cover_share_of_waste_pct, narrow_advance_ft_per_day, narrow_top_sqft, narrow_cover_cy, cover_reduction_pct, total_passes

Related tools