Asphalt Paver Speed and Production Rate

Tons per hour and lane-feet per hour a paver lays at a given screed width, depth, and forward speed.

Run the calculator

Example

You enter

You get

Details, formula, and sources

With the daily output - the production the asphalt-tonnage takeoff assumes and that sizes the plant delivery and truck rotation.

tons_per_hour = speed x working_min x width x (depth/12) x density / 2000; lane_ft_per_hour = speed x working_min; daily = hourly x hours.

Paving production identity by name (production = laydown area rate x compacted density); NAPA laydown-rate practice.

The paving production identity is published earthmoving / paving practice; NAPA guides free at asphaltpavement.org.

Estimate. AHJ and licensed professional govern.

Field names used by the API: speed_fpm, width_ft, depth_in, density_pcf, eff_min_per_hr, hours_per_day, tons_per_hour, lane_ft_per_hour, daily_tons, daily_lane_ft