Cold-Planing (Milling) Production and RAP Tonnage

Square yards per hour a cold planer cuts and the reclaimed-asphalt (RAP) tonnage it makes, which sizes the haul fleet.

Run the calculator

Example

You enter

You get

No published worked example is on file for this calculation. It is checked against a hand-worked derivation of its method and an independent reference test.

Details, formula, and sources

Scopesy/hr = drum width x speed x 60 x efficiency / 9; RAP tph = sy/hr x depth x density x 0.75 / 2000. A 7 ft drum at 30 ft/min covers 980 sy/hr, and a 4 in cut of 148 pcf pavement is ~218 tph of RAP - a truck every three minutes, or the mill stops. Field conditions govern the efficiency.

Formula or tablesy_per_hr = drum_width_ft x speed_fpm x 60 x efficiency / 9; spread_lb_per_sy = depth_in x density_pcf x 0.75; rap_tph = sy_per_hr x spread_lb_per_sy / 2000.

Source and editionCold-planing production identity by name (area rate from drum/speed/efficiency; RAP from area rate x spread); first-principles production arithmetic.

Free accessThe production and RAP geometry are public first-principles arithmetic; the efficiency comes from field conditions.

What governsEstimate. AHJ and licensed professional govern.

API field namesdrum_width_ft, speed_fpm, depth_in, density_pcf, efficiency, sy_per_hr, spread_lb_per_sy, rap_tph