Dozer Ripper Loosening Production Rate

Bank cubic yards per hour a dozer ripper loosens in place from the shank spacing, penetration.

Run the calculator

Example

You enter

You get

Checked against published worked examples from: Caterpillar.

Details, formula, and sources

ScopeBank cubic yards per hour a dozer ripper loosens in place from the shank spacing, penetration, and speed - the loosening step that feeds the push, load, and haul spread. Ripping fractures rock and hardpan; it does not move it. The operator judges rippability.

Formula or tablecross_section_ft2 = spacing_ft x penetration_ft; production_bcy_hr = cross_section_ft2 x speed_fpm x 60 x efficiency / 27 (60 min/hr, 27 ft^3/cy fold the units); with a pass length and turn time (Cat timing method): production = (cross_section_ft2 x pass_length / 27) x 60 / (pass_length / speed + turn) x efficiency.

Source and editionSwept-prism production identity by name (loosened volume = ripped cross-section x travel rate); first-principles unit-folding arithmetic.

Free accessThe swept-prism production identity is published earthmoving practice; the 60 and 27 unit constants are exact.

What governsEstimate. AHJ and licensed professional govern.

API field namesspacing_ft, penetration_ft, speed_fpm, efficiency, cross_section_ft2, production_bcy_hr