Trench Spoil Pile Setback and Surcharge

Required spoil-pile setback (the larger of the OSHA 2 ft minimum and the depth-based surcharge), the pile toe spread.

Run the calculator

Example

You enter

You get

Checked against published worked examples from: OSHA 29 CFR 1926.651(j) / Subpart P.

Details, formula, and sources

ScopeRequired spoil-pile setback (the larger of the OSHA 2 ft minimum and the depth-based surcharge), the pile toe spread, and the total clear distance from the trench edge.

Formula or tablebase_halfwidth = spoil_height / tan(repose); setback = max(min_setback, trench_depth); total_clear = setback + base_halfwidth.

Source and editionOSHA 29 CFR 1926.651(j) (2 ft spoil setback) and Subpart P (protective systems) by name; first-principles geometry.

Free accessOSHA 1926 Subpart P is free at osha.gov. The 2 ft minimum is code text.

What governsEstimate. AHJ and licensed professional govern.

API field namestrench_depth_ft, spoil_height_ft, repose_deg, min_setback_ft, base_halfwidth_ft, setback_ft, total_clear_ft