Change Order Price with Overhead and Profit

Change-order price = direct cost x (1 + OH%) x (1 + profit%).

Run the calculator

Example

You enter

You get

Details, formula, and sources

The compounded markup. $10,000 direct at 10% and 10% -> $12,100 (markup $2,100, 17.4% gross margin); the additive method gives $12,000. Applied to a $500K contract -> $512,100 new total. The contract's general conditions govern the allowed markup.

price = direct x (1 + OH%) x (1 + profit%); markup = price - direct; margin% = markup/price x 100.

The change-order overhead-and-profit markup (compounded) from construction estimating practice / AIA G701, by name.

Overhead-and-profit markup on a change order is standard construction estimating; the allowed rate and method are in the contract.

Estimate. AHJ and licensed professional govern.

Field names used by the API: direct_cost_usd, overhead_pct, profit_pct, current_contract_usd, price, markup, new_contract