Retainage Withheld and Net Payment (AIA G702/G703)

What is withheld from this draw, what gets paid, and what has piled up so far.

Run the calculator

Example

You enter

You get

Checked against published worked examples from: M. Purdy, Public Contracting Blog (WA RCW 60.28).

Details, formula, and sources

ScopeRetention this period = work x retainage rate, net payment = work - retention, cumulative = prior + this. $100,000 draw at 10% withholds $10,000 (net $90,000), cumulative $50,000 on $40,000 prior; a 5% job withholds $5,000. Retainage is earned money held until acceptance; the contract and certified payment govern.

Formula or tableretention_this = work x rate%; net_payment = work - retention_this; cumulative = prior + retention_this.

Source and editionThe retainage withholding and net-payment computation on an AIA G702/G703 progress application, by name.

Free accessRetainage on a progress draw is a standard published construction-billing computation (AIA G702/G703).

What governsEstimate. AHJ and licensed professional govern.

API field nameswork_this_period_usd, retainage_pct, prior_retained_usd, retention_this, net_payment, cumulative_ret