Data Center PUE and Cooling Overhead

Computes total facility load, PUE, DCiE, overhead, annual energy cost, target-PUE savings.

Run the calculator

Example

You enter

You get

Checked against published worked examples from: The Green Grid.

Details, formula, and sources

ScopeComputes total facility load, PUE, DCiE, overhead, annual energy cost, target-PUE savings, and the ratio trap when useful IT load falls faster than fixed overhead. The worked hall saves $122,640 per year while PUE worsens from 1.52 to 1.55. Annual metering and the site's measurement boundary govern.

Formula or tabletotal facility kW = IT + cooling + UPS loss + miscellaneous; PUE = total/IT; DCiE = IT/total; annual energy = total x 8,760.

Source and editionThe Green Grid PUE/DCiE definitions and ASHRAE data-center energy guidance. The site's declared metering boundary and measurement category govern.

Free accessAn energy ratio and component sum; The Green Grid publishes the PUE definition publicly.

What governsEstimate. AHJ and licensed professional govern.

API field namesit_load_kw, cooling_kw, ups_loss_kw, miscellaneous_kw, tariff_per_kwh, target_pue, reduced_it_kw, reduced_cooling_kw, reduced_ups_loss_kw, pue, dcie_pct, annual_cost, target_annual_savings, reduced_pue, reduced_annual_savings